You are here: Home Status

Status

List of deliverable items for Phase 1

Deliverables - Phase 1 Delivery date WP Responsible Partner Status
Generic Permafrost Website (GPW) 31 Mar. 2016 900 ZAMG completed
Requirements Baseline (RB) document 31 May 2016 100 UIO completed
Ground Data Documentation (GDD) 31 May 2016 100 AWI completed
Progress Meeting 1 - User Requirements Review
Observation Strategy Document v1 +
Updated Procurement Plan
31 Aug. 2016 200 H20 completed
Design Justification File (DJF-V1) 30 Sept. 2016 300 AWI completed
Technical Specifications 30 Sep. 2016 300 Gamma completed
Progress Meeting 2 - Review Design Engineering
Design Definition File (DDF) 30 Nov. 2016 300 AWI completed
Acceptance Test Document 31 Jan. 2017 400 AWI
Subset of products for Demonstration Scenario (SDDS) 31 Jan. 2017 400 ZAMG completed
Updated Design Justification File (DJF-V2) 31 Jan. 2017 400 UIO completed
Prototype Validation and Assessment Report (PVAR) 31 Jan. 2017 400 H2O completed
1st User Workshop
Summary Report of User Workshop (SRW1) 28 Feb. 2017 900 ZAMG completed
Critical Design Review Report (CDR) 28 Feb. 2017 400 ZAMG completed
Website for Product Dissemination (DW)
31 Mar. 2017 400 AWI completed



List of deliverable items for Phase 2

Deliverables - Phase 2 Delivery date WP Responsible Partner Status
Qualification Review Report (QRR) 30 Sep. 2017 500 AWI
Demonstration dataset v1 (DDS) 30 Sep. 2017 600 Gamma
2nd User Workshop
Summary Report of User Workshop 31 Oct. 2017 900 ZAMG
Production and Validation Report (PVR) 31 Jan. 2018 600 UIO
Progress Meeting 4 - On Site Acceptance Test
Permafrost Information System (PS) 31 Jul. 2018 500 AWI
Acceptance Review Report 31 Jul. 2018 500 AWI
3rd User Workshop
Summary Report of User Workshop 31 Aug. 2018 900 ZAMG
Utility Assessment Report 31 Jan. 2019 600 UIO
Demonstration Data Set (DDS-V2) 31 Jan. 2019 700 ZAMG
Observation Strategy Document v2 31 Jan. 2019 800 ZAMG
Final Report (FR) 31 Jan. 2019 800 ZAMG
Contract Final Review